After we changed our strategy on HOW we are fencing
our hatchery area in between nesting seasons (driftwood instead of boards), we actually prevented people
stealing our stronghold and managed to keep the area pretty much
Olive-Ridley-nest-free.
In the beginning of November we started to remove ¾
of the hatchery sand, sifted and cleaned the remaining sand, and started to sift
and bring-up clean sand (naturally disinfected by the sea) from the water-line
to fill-up the hatchery.
The hatchery stretches over an area of 7.5x4.5m
and 1m depth, and will have room for 30 Leatherback nests.
|
Removing the sand of the hatchery.... |
All of our volunteers, and also the volunteers
from the MINAET station were of great help, and showed an amazing work
attitude, and I would like to use this space here to thank them all. THANK YOU
VERY MUCH!!!!
It were tough times, since all of us worked during
the night, and still got up at 5 am to work in the hatchery up until around 8-9
am. We did this for around 3 weeks, and everyone was sleep deprived and
physically on their limits. But the reason for constructing the hatchery, to build
an incubation station for a critically endangered species, that otherwise would
have no hatching success in its naturals nests, seemed to be motivation enough
for most of us.
|
Jairo measuring the dimensions of the hatchery. |
So in less time than anticipated we were able to
finish the sifting and shovelling part of the construction, and erected the
shade for the hatchery around on November 11
th. The shade helps to
keep the incubation temperatures below the lethal 32°C, which is essential for
the hatching success inside the hatchery.
While the weather during the construction promised
that summer would start soon, we were all up for a surprise when the rains
started again, and drenched us during our nightly patrols, but also helped to
restore the important humidity levels inside the hatchery.
So now our hatchery is done, everyone is
recovering from their blisters, and is trying to catch-up on some sleep.
|
......and bringing up clean sand from the waterline. Go Yeudi and Gredi! |
|
Markus working hard |
|
Andrey distributing and mixing the sand. |
|
Putting up the frame for the shade. |
|
Some acrobatic acts on the side by Chris and Jairo to replace a ladder. |
|
Frame for hatchery almost done. |
|
Sewing the shade of the hatchery. (Jairo and Miriam) |
|
Compacting the sand in the hatchery. Work can also be fun. |
|
Measuring the squares, and preparing for the first nest. |